The AI boom was paid for with cash. Now it runs on credit

The AI boom

Big Tech's AI build-out is now being paid for with bonds, private loans and off-balance-sheet deals. The warning signs are in the debt markets. For Gulf investors, now among the largest backers of that build-out, the real question is who ends up holding the risk.

[For more news, click here]

For three years, the AI boom was a story about stock prices. If the bulls were wrong, shareholders would lose money and everyone else would watch.

That story ended this autumn. The AI boom is now a credit story, and credit stories travel. When debt goes bad, lenders pull back, refinancing gets harder, and the trouble reaches companies that never bought a single chip.

The turn came into focus on November 5, when the Nasdaq 100 lost roughly $2.5 trillion in market value in one session. The more telling moves came in the bond market. Within days, a European bank was shopping data center loans and an AI cloud company's bonds were trading at distressed levels. Some banks that had lined up to fund AI projects told Reuters they were now reluctant to finance more.[1]

I spend my working days looking at how deals are financed rather than how stocks trade, and my reading is this: the question is no longer whether AI demand is real. It is. The question is whether the debt raised against that demand is built to survive a delay. On the evidence of this autumn, much of it is not. And the Gulf, which has become one of the largest sources of capital for this build-out, has a strong interest in how this plays out.

From cash machines to borrowers

The spending is vast. Amazon expects about $220 billion of capital expenditure this year, and Microsoft about $170 billion for the calendar year. TwentyFour Asset Management estimates total AI capital spending above $750 billion in 2026. Morgan Stanley expects $1.66 trillion next year.

For most of this boom, the world's most profitable companies paid from their own pockets. No longer. Goldman Sachs says the hyperscalers collectively had negative free cash flow in the third quarter, as capital spending exceeded operating cash flow.[2] The gap is being filled with debt.

Goldman counts about $296 billion of hyperscaler bond issuance so far in 2026. It expects $440 billion next year, plus about $300 billion of project-level debt.[2] The IMF notes that hyperscalers' share of global investment-grade bond issuance has jumped to 10%, from less than 1% before 2024.

Borrowing to build is not wrong. Railroads and power grids were built on credit. But it changes who carries the risk if the returns come late.

In my view, the bigger change is not the size of the numbers but what borrowing does to discipline. When a company spends its own cash, a bad project shows up as lower profits, quickly and in public. When it borrows, especially through a separate vehicle, a bad project shows up years later as a refinancing problem, and often on someone else's balance sheet.

Where the risk is hiding

The danger is not Microsoft defaulting. It sits in the weaker parts of the system, and in debt that is hard to see.

The leveraged middle. Oracle is building data centers for a reported $300 billion OpenAI contract. It has issued $118 billion of long-term debt and carries $39 billion in capital and lease obligations, according to FactSet data cited by CNBC. Analysts' consensus forecasts put its free cash flow at negative $23.7 billion this year. S&P rates it BBB-, one notch above junk.[3] Its default-insurance costs hit records in October, at levels one S&P Global analyst likened to junk credit.

The neoclouds. CoreWeave, which rents out Nvidia chips, is the system's stress gauge. Its 2032 bonds yielded above 16% in early November, even as its business grew.[4] After its third-quarter results on November 10, the company raised its 2026 revenue guidance. Its chief executive said it would not use the unsecured bond market at current yields. Instead, it is reportedly seeking a secured loan of at least $4 billion, backed by chips and a Meta contract.[5] That tells you where the market now draws the line. Lenders will fund the hardware and the contract, but they are far more cautious about the company itself. Rival Nebius shelved a planned high-yield bond.

Debt off the books. Meta's Hyperion campus in Louisiana is being built by a joint venture with funds managed by Blue Owl, financed with about $27 billion of bonds. Meta owns 20% and does not consolidate the venture. But Meta will lease the campus and has given the venture a residual value guarantee covering its first 16 years.[6] Its latest quarterly filing puts the maximum it could owe under such guarantees, across its data center ventures, at $41.5 billion. That is up from $28.1 billion at the end of 2025.[7]

Across the system, the IMF counts 14 deals since 2023 in which hyperscalers invested about $300 billion of equity in financially weaker AI firms. Those deals carried $650 billion of debt, in exchange for $1.4 trillion of future revenue commitments. The same few companies are investors, lenders, suppliers and customers to one another. That works while demand rises. It concentrates losses if demand falls short.

The lenders are blinking

The clearest signal comes from banks. ING is seeking buyers for about $500 million of data center loans, Bloomberg reported. The package includes a $25 million piece tied to the Stargate site in New Mexico, as well as debt linked to Vantage Data Centers and CyrusOne, with bids due on November 19.[8] At JPMorgan, loans backed by "other income-producing properties", a category that includes data centers, reached about $29 billion at the end of the third quarter. That is 12% of its commercial real estate book, up from 8% three years ago.[1]

A lawyer who works on these deals told Reuters that investors' books "have become full." A strategist at SMBC described "financiers looking to exit before the door shuts." Bank of America says spreads on 10-year hyperscaler bonds have widened about 50 basis points this year. Comparable non-AI companies have seen about 20.

Politics now matters too. After this month's midterms, Texas's governor-elect called for a data center moratorium until consumer protections are in place. Goldman estimates proposed or enacted state moratoriums could affect about 45% of planned US capacity.[2] A data center without a permit or a grid connection cannot generate the cash its lenders were promised.

Regulators saw this coming. The IMF warned in October that an AI correction could be amplified by "rising leverage, concentrated exposures, and circular financing arrangements." The Bank of England has flagged the "complexity and opacity" of AI debt structures.

This is not 2008, yet

The optimists have a case. The biggest borrowers are among the strongest companies on Earth, and investors still compete for their bonds. Morgan Stanley says spreads have tightened on most names since the latest deals, and sees good value in top-quality hyperscaler debt. The IMF's stress test found the global banking system would stay resilient in a severe AI-led correction. Demand is real, too. On November 17, Nvidia reported quarterly revenue of $115.8 billion, up 103% from a year earlier, and data center revenue of $107.6 billion. It guided to about $130 billion for the current quarter.[9]

But strong chip sales do not settle the credit question. They show that money is being spent. They do not show that the borrowers will earn it back on time. The better comparison is the dot-com bust, and it is not reassuring. The telecom builders of 1999 also had real customers, and their fiber was eventually used. The problem was that the debt came due before the demand arrived, and lenders broke before the technology did. Today, chips wear out in a few years, while much of this debt runs 15 to 30 years. That mismatch is the core of the risk.

My own assessment is that the stress will not start with the hyperscalers, and it will not start with the banks. It will start in the layer between them: the special-purpose vehicles, neoclouds and developers whose revenue depends on one or two tenants, and whose debt was priced on the assumption that those tenants would renew. When I look at any of these deals, I ask three questions. Does the lease run as long as the debt? How much of the collateral is land, power and buildings, and how much is chips that will be obsolete before the loan is repaid? And is the big-name tenant's support a guarantee from the parent company, or only a lease signed by a subsidiary that can walk away? A project that fails two of those three tests is where I expect the first losses.

What this means for the Gulf

The Gulf is not a bystander to any of this. Abu Dhabi's MGX is a founding investor in the US Stargate venture. It was also part of the consortium, with BlackRock's Global Infrastructure Partners and the AI Infrastructure Partnership, that completed the roughly $40 billion acquisition of Aligned Data Centers in July.[10] Saudi Arabia's Public Investment Fund has launched HUMAIN to build national AI capacity.

At home, the UAE is hosting Stargate UAE, a 1-gigawatt AI cluster within the planned 5-gigawatt UAE-US AI Campus in Abu Dhabi. G42 is building it, and OpenAI and Oracle will operate it. The first 200 megawatts are expected to come online this year.[11] G42 has said work is progressing as planned, and that the project's specifics remain under continuous review in line with the security, resilience and operational standards expected of critical infrastructure at this scale. For investors and lenders, that kind of resilience planning is a positive. It is exactly what long-term infrastructure finance should reward.

Gulf capital is also well placed for what comes next. As Western banks sell down data center loans, someone will buy them. Gulf sovereign funds and family offices, which already invest in global private credit and increasingly own data center platforms directly, are natural candidates.[10] I see this as a potential opportunity for disciplined investors. Well-structured loans to strong projects, bought from motivated sellers, can be priced attractively. The key is discipline: price each loan on its own merits, and don't treat it as a vote of confidence in AI as a whole.

That involvement reaches the region through three channels, and each calls for a different approach.

Gulf investors: know which layer you own. Owning hyperscaler shares, lending to a joint-venture vehicle and holding units in a private credit fund can look like three ways of backing the same theme. They are not. They sit at very different points in the capital stack and behave very differently in a downturn. For any investor active across equity, credit and funds, the risk is holding the same exposure through several channels without a consolidated view. An investor that holds a stake in a data center platform directly, and also owns private credit units that bought the same project's loans from a bank, has doubled its exposure without deciding to. Good practice is straightforward: map look-through exposure to AI infrastructure across equity, credit and fund commitments, and set a single limit for it.

Regional data center projects: real advantages, same financing principles. The Gulf has what US projects are now struggling to secure: competitive power, available land, sovereign backing and efficient permitting. That is a genuine edge, and it makes Gulf projects far less exposed to the kind of moratorium risk now emerging in the United States. But the core mismatch travels with the chips. A campus financed over 15 to 20 years and filled with processors that lose most of their value in four or five carries the same duration risk wherever it is built. Like large projects anywhere, Gulf projects also need to plan around access to advanced chips under export licensing, and around a concentration of revenue in a small number of anchor tenants. I would want to see chip financing separated from real estate financing, with shorter tenors and its own repayment schedule, and a diversified tenant base over time.

Regional banks and capital providers: two different roles. Gulf banks could take part in this build-out in two distinct ways, and the considerations are different.

The first is buying loans that Western banks are selling. Gulf banks are well capitalized and liquid, which makes them natural buyers. Here, the main discipline is information. A loan a European bank is keen to sell is not necessarily a bad loan, but the seller knows it better than the buyer does. Banks buying these assets should underwrite them on contracted cash flow rather than on capacity built, and push for parent-level rather than project-level support.

The second is financing data centers in the region itself. Here, the scale is manageable. In Saudi Arabia, one Alvarez & Marsal estimate puts the banking system's likely base-case data center lending at $3.5 billion to $7 billion, under 1% of banks' private-sector loan book.[12] The challenge is concentration rather than capacity. Larger pipelines will draw on a wider mix of funding beyond bank lending, and sensible single-name limits matter for any lender.

Islamic finance offers useful tools across both, as long as each one is matched to the right stage of a project. Istisna'a structures suit the construction phase. Ijara, a lease-based structure, mirrors how data centers earn revenue once they are operating. Sukuk can refinance completed projects and reach institutional investors who do not lend directly, often at longer maturities than banks offer.[13] Because these structures tie funding to identifiable assets, they work best when the underlying asset is the long-lived infrastructure, meaning the building, the power connection and the cooling systems, rather than chips that depreciate quickly.

Handled well, this is an opportunity rather than a threat. The Gulf has the patient capital and the energy that the AI build-out needs, and it is well placed to be the disciplined lender in a market that has not always been disciplined. The investors who do best from this cycle will be the ones who price in the delay, not just the promise.

What needs to happen now

None of this means a crash is coming. It means the important questions have moved to the bond desk, and policymakers and investors everywhere should follow.

Show the full picture: Companies should report data center lease guarantees and joint-venture obligations as one clear figure, not scattered across footnotes. Follow the risk: Private credit funds are buying the loans banks sell. Regulators need to know where that risk ends up, and how much returns to banks through lending to those funds. Price the politics: Lenders and rating agencies should stress-test for permitting delays, power shortages and local moratoriums. Look through the structure: Investors and lenders should track AI infrastructure exposure across equity, direct lending and fund commitments as one number, and stress-test it for a two-year delay in AI revenue.

The next tests are already here. Nvidia's results show that spending is still accelerating. The outcome of ING's loan sale will show what buyers are willing to pay for data center debt. Morgan Stanley expects far heavier AI borrowing in 2027. If investors keep lending on today's terms, the boom rolls on. If they demand more, the weakest borrowers will feel it first.

For years, the question was whether AI would change the world. The question now is more prosaic, and more urgent: who is holding the debt if the payoff takes longer than promised? For the Gulf, with its patient capital and long-term perspective, the opportunity is to be the one asking that question first.

Contributed by Mr. Sayed Adnan

Sayed is the Chief Business Officer of Graystone Capital, where he leads the firm's business development, deal origination, and strategic partnership functions across all 12 of its active markets. As one of the founding architects of the Graystone platform. With a career grounded in financial advisory, capital markets origination, and cross-border business development across the Gulf Cooperation Council, Southeast Asia, and South Asia, Sayed has built and maintained an institutional network spanning corporates, family offices, government-related entities, banks, and financial institutions. As CBO, Sayed is also the principal custodian of Graystone Capital's client relationships, the individual to whom the firm's most important counterparties turn when they require a capital solution, a strategic introduction, or a trusted perspective on a complex financing situation.

Related Articles

IFC to Advise on Yamna's $1.3 Billion AI Data Center Project in Oman

Brookfield Opens Doha Office as Qatar Advances $20 Billion AI Infrastructure Plan

Exclusive: How Edge AI Is Reshaping Data Sovereignty Across Saudi Arabia and the UAE

Related Articles

Abu Dhabi Launches AI Tools to Rewrite Arabic Texts for Different Reading Levels
AI

Abu Dhabi Launches AI Tools to Rewrite Arabic Texts for Different Reading Levels

Conceptual Gulf data center with a processor and controlled access gateway connecting to international computing customers.
AI

Ownership without Control - How the Gulf 'AI independence' is still tied to US regulations.

Conceptual illustration of Arabic and Latin letterforms entering an AI verification prism with a gap in one data path.
AI

Why English-Only Testing Misses Arabic AI Failures

Raghav Sehgal, General Manager Middle East at Model ML
AI

Exclusive: Raghav Sehgal on the Shift Towards Agentic AI in Financial Services

us
AI

US offers $50 million to support Malaysia’s sovereign AI cloud initiative

AI generated image
AI

Jordan Is Building More Than an AI Campus. It Is Building the Stack Around It